TENNIS COURT 1
November 10, 2020
GUY MASON RECREATION CENTER
December 23, 2019

Project Details

Description

Cut and dispose 2ft of asphalt- Same sides where the rubber is being demo, just to extend the opening to 3ft total
Power wash surround the playground
Demo and dispose (2) red benches from the playground area. Patch the floor as needed.
Furnish and install (2) new 6 Ft benches-4 weeks lead time
Pour 3-4"new asphalt on excavated areas
Work to be done over the weekend and finish by Monday 10/14/2019

See this project in 360